We’ll begin to connect our first subscribers in a matter of weeks, but you can now visit our website to get a clear idea of the services CVFiber will offer and how much they will cost. Out in the field, construction is continuing to progress, and we’re looking forward to full construction and connecting our…

Consolidation Time

We’ve entered something of a seasonal pause in construction, so this month’s activity is devoted to the necessary stuff: Design and financial planning, ordering materials, preparing for the onset of full construction this spring, adding staff, and preparing to launch our marketing and subscription programs. What it may lack in excitement it more than makes…

March News: Hiring, Webinar, and More

CVFiber leadership held a webinar on March 1 that provided a thorough update on our progress. You can read a brief summary below; the entire presentation, including numerous illustrations, is available online at https://cvfiber.net/2023/02/webinar-update-on-progress Here’s a rundown of the news in this update. Construction Update Webinar Available We continue to move forward with construction on…

There’s Always Something New

Those words were spoken recently by CVFiber Executive Director Jennille Smith, and they are definitely true. We continue to lay strand and fiber in Calais even as we look ahead to full construction this spring and the connection of our first subscribers, most likely in late spring. At the same time, we’re riding herd on…

We’re Off and Running

We’re Off and Running

Big news: CVFiber has begun construction on our 1,200-mile fiber network! We’ll begin offering service to our first customers this spring. 2023 is off to a good start, thanks to our recent mild weather. We’re planning to keep the work going continuously throughout the year. This is the time when all the dreams, the planning,…

On Your Mark… Get Set…

We are about to start construction on our 1,200-mile fiber network. Every week, sometimes every day, more clearances are received, more contracts are signed, and more and more materials fill our warehouse space. We’re also doing the work needed to turn CVFiber from a behind-the-scenes planning operation to a public-facing service provider. There’s some exciting…

Getting Our Ducks in a Row

As we prepare to begin construction on our 1,200-mile fiber network, we’re taking care of a long list of preliminaries. There’s a sobering array of details to pin down, potential obstacles to remove, and agreements to be finalized. We’re developing inventory control systems to handle all the materials needed to build the network as ordered…

Making Progress on Every Front

Thanks to the steady progress we’ve made in recent weeks, we are now confident that construction of our high-speed fiber network will begin this fall. We’re aiming to build roughly 100 miles this year and begin connecting subscribers in early 2023. The pace is as frenetic as that Lucy Show scene at the candy wrapping…

Blazing the Broadband Trail

As the beginning of construction draws closer on our 1,200-mile fiber network, the challenges are mounting up. This is not unexpected. Building the network is a complicated process with many interdependent parts. We are ordering materials, finishing up pole inventory, conducting make-ready work, refining design plans, negotiating with pole owners for network access, and obtaining…

Firing On All Cylinders

CVFiber continues to make progress on all fronts toward the beginning of construction this fall. It’s a busy time, but it’s so rewarding to be this close to bringing high-speed Internet to central Vermont. As the song goes, “The future’s so bright, I’ve gotta wear shades.” Here’s the rundown: CVFiber has chosen marketing packages to…